SHUTTLE PROCESSING STATUS REPORT: S05-017

NASA’s Space Shuttle fleet is housed and processed at Kennedy Space Center (KSC), Fla.

Mission: STS-114 – 17th ISS Flight (LF1) – Multi-Purpose Logistics Module
Vehicle: Discovery (OV-103)
Location: Launch Pad 39B
Launch Date: Launch Planning Window July 13 – 31, 2005
Launch Pad: 39B
Crew: Collins, Kelly, Noguchi, Robinson, Thomas, Lawrence and Camarda
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Following Space Shuttle Program management discussions, a plan was laid out reflecting how the program will move toward the STS-114 Return to Flight launch.

Preparations are under way for a tanking test no earlier than the week of May 15 to continue troubleshooting two issues that arose during a tanking test on April 14. Engineers are evaluating the liquid hydrogen sensors in the tank that gave intermittent readings during last month’s test. These sensors serve as fuel gauges to notify the Space Shuttle Main Engines to shut down when propellants reach a certain level in the tank. This is critical in the safe operation of the main engines. Engineers are continuing to evaluate a liquid hydrogen pressurization relief valve that cycled more times during the tanking test than is standard. This valve opens and closes to ensure the liquid hydrogen stays at the correct temperature.

Following the tanking test, technicians will begin preparations for rolling Space Shuttle Discovery back to the Vehicle Assembly Building (VAB). Once in the VAB, Discovery most likely will be destacked from its External Tank (ET) and lowered into the transfer aisle. This will be the eighth destacking in the program’s history following a rollback.

In parallel, the ET (ET-121) and Solid Rocket Boosters scheduled to fly with orbiter Atlantis on mission STS-121, is being prepared to fly with Discovery on mission STS-114. The preparation of ET-121 is in the VAB’s checkout cell. A new heater will be added to the feedline bellows to minimize the potential for ice and frost buildup. This heater modification will be installed over the next 24 days. Once Discovery returns to the pad, another tanking test may be performed to test the new modifications.

Mission: STS-121 – 18th ISS Flight (ULF1) – Multi-Purpose Logistics Module
Vehicle: Atlantis (OV-104)
Location: Orbiter Processing Facility Bay 1
Launch Date: Lighted Launch Planning Window September 9 – 24, 2005
Launch Pad: 39B
Crew: Lindsey, Kelly, Sellers, Fossum, Nowak and Wilson
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Processing continues on Atlantis in Orbiter Processing Facility bay 1 for its mission, designated STS-121, to the International Space Station. Vehicle power-up testing is about 70 percent complete. Closeouts continue in the forward and aft areas of the orbiter.

A new Thermal Protection System seal has been added in the nose and main landing gear. Hydraulics were powered up, and preparation continues for a scheduled landing gear functional test. Servicing of the potable water system is finished.

Port and starboard Manipulator Positioning Mechanisms were successfully cycled from full stow to full deploy. These are the pedestals that hold the Remote Manipulator System, or Shuttle robotic arm, and the Orbiter Boom Sensor System in the payload bay. Rudder Speed Brake Thermal Protection System tile and blanket installation continues. Atlantis will likely fly with ET-119. The ET is scheduled to arrive from the Michoud Assembly Facility in New Orleans next month. Stacking of the Solid Rocket Boosters is complete in high bay 1, and the joint closeouts are under way.