Discovery is Ready to Roll

At NASA's Kennedy Space Center in Florida, preparations for space shuttle Discovery's rollout from the Vehicle…

Discovery Rolls to Pad Tonight

At NASA's Kennedy Space Center in Florida, space shuttle Discovery will be moved from the Vehicle…

Discovery on Schedule for Monday Rollout

Technicians in NASA Kennedy Space Center’s Vehicle Assembly Building have completed all mechanical work and foam…

Tank Mods Finished for Discovery’s Tank

Technicians in NASA Kennedy Space Center’s Vehicle Assembly Building have completed all mechanical work and foam…

Modifications to Tank to be Completed Thursday

Technicians in NASA Kennedy Space Center’s Vehicle Assembly Building are expected to wrap up all modification…

Foam Spraying and Trimming Under Way

Technicians in NASA Kennedy Space Center’s Vehicle Assembly Building are expected to wrap up all modification…

Stringer Modifications on External Tank to Wrap Up This Week

In the Vehicle Assembly Building at NASA's Kennedy Space Center in Florida, technicians are expected to…

Discovery Rollout Planned for Jan. 31

Discovery’s rollout to Launch Pad 39A is planned for Monday, Jan. 31. First motion is at…

Modifications Complete on 61 of 94 Stringers

Technicians in the Vehicle Assembly Building at NASA's Kennedy Space Center in Florida completed radius block…

Space Shuttle Program baselines STS-135

On Thursday, the Space Shuttle Program baselined the STS-135 mission for a target launch date of…