Managing Capital Investments and Resources for Large, Complex Satellite Development Efforts

Abstract: Once the schedule was baselined and the primary, secondary, and tertiary critical paths (at least) were established: Identified what entity control which portion of the schedule reserve Dollarized the time associated with the schedule reserve and segregated it off from other budget reserves authorization to spend only came when authorization to utilize the time was given Created a process to manage the control of these resources This process was above and beyond the typical schedule controls …