China Spallation Neutron Source: Beam power reaches design goal ahead of schedule

The China Spallation Neutron Source (CSNS) conducted on-schedule beam commissioning from Feb. 3 to Feb. 28, thus achieving its design goal of 100kW 18 months ahead of schedule. Since then it has conducted stable operations at 100 kW.


Click here for original story, China Spallation Neutron Source: Beam power reaches design goal ahead of schedule


Source: Phys.org